In May 2019 GP & Sons Demolition was engaged to complete the demolition of Y Suites Waymouth Street
- Synergy Construct
- Waymouth Street Adelaide
- May 2019 – July 2019
Key Project Facts :
- Approx. 500 T of contaminated demolition waste with Asbestos needed to be removed
- Remove existing Asbestos as per intrusive register
- Demolition of 3 story buildings
- Removal of all concrete structures
- Removal of 6000 T of mixed waste contaminated soil
- Supply and compact piling platform pad
- Removal of earthworks soil